How storage plants participate in the Greek electricity market

News

Share

From trial operation to commercial operation

Commissioning tests and trial operation. Before a storage entity can enter commissioning tests or trial operation, the technical decisions of the Independent Power Transmission Operator (IPTO) require it to be preregistered in IPTO’s Register of Dispatchable Storage Entities. Once the plant is energised, checks cover its grid connection, power measurements and the communications it uses to receive and execute dispatch instructions. Depending on the service, these checks cover the remote terminal unit (RTU) link to IPTO’s automatic generation control (AGC) system or the web services link to its Balancing Market platform.

For commissioning tests and for trial operation lasting more than four hours, IPTO submits the scheduled purchases or sales to the Day-Ahead Market of the Hellenic Energy Exchange (HEnEx) as priority price-taking (PPT) orders. Once a plant covered by this procedure has passed the required checks, the relevant system operator issues a certificate confirming completion of trial operation.

Who represents a storage plant at HEnEx and IPTO?

On the HEnEx Day-Ahead and Intraday Markets, buy and sell orders may be submitted by the plant owner, if registered as a market participant, or by an aggregator authorised to represent storage plants. Either may represent a large storage plant individually or represent a storage portfolio. Under the Balancing Market Rulebook, a storage plant is classified as large if it is connected to the Hellenic Electricity Transmission System and has a maximum injection capacity of 10 MW or more.

A balancing service provider (BSP) is a market participant with balancing service entities at its disposal through which it can provide balancing services to IPTO. The BSP registers with IPTO, enters into a contract with it and submits bids for balancing capacity or balancing energy. A balancing service entity is the unit or portfolio technically capable of delivering the service. Prequalification establishes which services each entity can provide. A BSP may represent several entities. Bids and dispatch instructions are separate for each one.

The balance responsible party (BRP) is financially responsible for imbalances. A licence holder that represents its own dispatchable storage plant must register with IPTO in the relevant capacities. If the holder delegates representation, the aggregator it appoints must be authorised to represent storage plants and registered as both a BSP and a BRP. The aggregator notifies IPTO of its agreement with the holder and identifies the entity and its meters. The holder may retain technical control of the plant.
Under the transitional provisions of Law 5287/2026, existing renewable energy or demand response aggregators covered by the law may register by submitting their licence and proof that they have applied to extend it to storage.

Capacity limit per person or corporate group. Through the end of 2029, Law 5299/2026 sets a 500 MW limit on the combined maximum injection capacity of battery storage plants within its scope. The calculation takes account of ownership, the revenue assignment agreements specified in the law and representation, including the interests of linked or partner enterprises. The exemptions in Article 10(11A) of Law 4685/2020 and Article 50B(8) of Law 4951/2022 apply.

Which HEnEx products are open to storage plants?

Decision E-38/2026 of the Regulatory Authority for Waste, Energy and Water (RAAEY) specifies the products and order types available to storage plants on the spot markets. In the markets for physical delivery, the owner or aggregator submits orders for the registered large storage plant or the relevant portfolio.

MarketProducts and order types available to storage plants
Day-Ahead Market (DAM) Single Day-Ahead Coupling (SDAC)Plants may submit 15-minute hybrid buy or sell curve orders with stepwise or linear segments, and block orders with 15-minute resolution. Hourly time-unit orders are unavailable to this category of participant.
Intraday auctions IDA1, IDA2 and IDA3Plants may submit 15-minute hybrid curve orders in all three auctions. IDA1 and IDA2 cover the full delivery day. IDA3 covers its second half.
Continuous intraday trading XBIDPlants may trade 15-, 30- and 60-minute products. They may also define a block of 2 to 30 consecutive periods of equal duration, with the same price and quantity for each period. The block is executed in full. The order book accepts limit, linked and iceberg orders.

In the Day-Ahead Market, a simple block order has the same acceptance ratio across all periods it covers. With linked block orders, acceptance of one order depends on acceptance of another. In an exclusive group of block orders, the sum of the acceptance ratios cannot exceed 100%. A circular block order links a buy order to a sell order, for example to pair midday charging with evening discharge. Both legs have the same acceptance ratio, but their volumes may differ to account for energy losses. Each entity may submit up to five block orders in total, including up to two circular pairs.

Adjusting a position. In an intraday auction (IDA) or in continuous intraday trading (XBID), a buy order that is executed can reduce the volume a plant is due to deliver after a sale in the Day-Ahead Market or an earlier intraday auction for the same delivery day. Equally, a sale can reduce the volume the plant is due to withdraw following an earlier purchase. Its net position for the delivery period determines its scheduled injection or withdrawal.

Example. A plant sells 2 MWh in the Day-Ahead Market for 20:00–20:15, scheduling an injection of 8 MW for 15 minutes. If it buys back 0.75 MWh in IDA1 for the same market time unit (MTU), its scheduled injection falls to 1.25 MWh, or 5 MW over the quarter-hour. Buying back the full 2 MWh brings its net position to zero.

Which balancing services can storage plants provide?

A storage plant participates in IPTO’s Balancing Market through its BSP. The plant owner or an authorised aggregator can take on this role.

The Balancing Capacity Market has six capacity products, measured in MW. The Balancing Energy Market has four activation products, measured in MWh. A plant responds to an upward activation by increasing injection or reducing charging. It responds to a downward activation by reducing injection or increasing charging.

IPTO reserve productCapacity directionBalancing energy
Frequency containment reserve (FCR)Upward and downwardNo separate energy bid
Automatic frequency restoration reserve (aFRR)Upward and downwardUpward and downward
Manual frequency restoration reserve (mFRR)Upward and downwardUpward and downward

In the Integrated Scheduling Process (ISP), capacity awards are added together separately for each direction. The totals must stay within the plant’s or portfolio’s declared injection and withdrawal limits. Participants declare and update those limits on IPTO’s Balancing Market platform.

When a dispatchable storage plant is awarded aFRR or mFRR capacity, its BSP must offer the corresponding balancing energy for the same quarter-hour and in the same direction. The obligation to submit an energy bid begins during the ISP, when the BSP submits the corresponding capacity bid.

Balancing energy products are settled on a pay-as-clear basis. Balancing capacity is settled on a pay-as-bid basis.

The two project groups and how operating aid is calculated

Before a supported plant receives its operating licence, RAAEY assigns it to one of two project groups, based on the minimum guaranteed storage capacity required in the tender in which it was selected, expressed in MWh per MW. The group provides the benchmark for calculating operating aid. Market orders are submitted by the plant or the representative of its trading portfolio.

Each group’s revenue calculation also includes unsupported plants that trade in the market (merchant storage), provided that the guaranteed capacity stated in their storage licence is within ±25% of the relevant tender minimum. Unsupported plants that participate through an aggregator’s portfolio are excluded from this comparison. A merchant plant is included solely for the purpose of calculating group revenue.

Who estimates market revenue? The Renewable Energy Sources and Guarantees of Origin Operator (DAPEEP) prepares the estimate and submits its recommendation and supporting study to RAAEY. IPTO, HEnEx and the Hellenic Electricity Distribution Network Operator (HEDNO) supply the data for which each is responsible. RAAEY sets the final figure in euros per MW for each project group and each year of the regulatory period.

How is aid calculated for each plant? The starting point is the plant’s reference revenue, set by its winning bid. The group’s estimated market revenue per MW is deducted from this figure, and the prescribed adjustments for additional revenue or losses are applied. Net revenue consists of receipts from electricity sales and balancing services after deducting costs such as electricity purchased for charging and market fees.

How does market performance affect a plant’s revenue? At the annual review, the group’s total net revenue is divided by the sum of the participating capacities of its plants. If group membership changes during the year, the calculation is made separately for each period. As a rule, the adjustment to operating aid reflects 100% of the difference between the group’s forecast and actual revenue. All else being equal, a plant that earns more per MW than the group average therefore keeps the benefit of its better performance. If the calculation produces a negative aid payment, the amount is repaid or offset.

First application in 2026. In Decision E-218/2026, RAAEY adopted the P75 scenario from DAPEEP’s study. Estimated market revenue was approximately €157,000/MW for a two-hour plant over the full 2026 calendar year and €101,000/MW for a four-hour plant in the second half of 2026. The two estimates cover different periods. The decision sets monthly aid separately for each plant according to the month in which its operating licence is issued.

Electricity storage at the heart of the energy transition
Articles

Electricity storage at the heart of the energy transition

The transition to a greener, more sustainable future is one of Greece’s most important energy policy goals. It will give the country the resilience it needs as crises become more frequent and help it compete internationally as conditions change. Greece must therefore make the most of its own energy resources, including renewables such as solar […]

Why do we need electricity storage?
Articles

Why do we need electricity storage?

Greece is expanding renewable generation and adapting its infrastructure under the Paris Agreement, the EU’s Green Deal and Fit for 55 package, and its own National Energy and Climate Plan (NECP) and Climate Law. It aims to make renewables the mainstay of its energy mix, reduce its dependence on fossil fuels by 2030 and end […]

The energy transition needs every ‘green’ megawatt-hour
Articles

The energy transition needs every ‘green’ megawatt-hour

Storing energy is no new idea. It has been part of the development of human civilisation throughout history. In its modern forms, energy storage is also essential to the energy transition. This explains the strong and sustained commitment, in Europe and internationally, to supporting large-scale energy storage technologies. That commitment was bound to have an […]